Off Airport Construction KY236 (Donaldson Highway) Widening Project 2/27/2023 7:30:00 AM 9/30/2025 5:00:00 PM
Landside Construction DHL 50 Acre Site Development 4/22/2024 7:00:00 AM 10/31/2025 6:00:00 PM
Landside Construction Fuel Farm Upgrade - Phase 7 12/2/2024 7:00:00 AM 12/31/2025 5:00:00 PM
Landside Construction North Cargo Development Site 8/12/2024 7:00:00 AM 7/31/2025 7:00:00 PM
Off Airport Construction KY236 Donaldson HWY Widening Project 12/4/2024 12:00:00 PM 9/30/2025 12:00:00 PM
Landside Construction Fiber, Energy & Dynamic Sign Project 1/3/2025 7:00:00 AM 7/31/2025 5:00:00 PM
Airside Construction O'Rourke BHS Demo 3/17/2025 12:00:00 AM 6/15/2025 12:00:00 PM
Landside Construction CVG Centre sidewalk repair 4/13/2025 7:00:00 AM 5/30/2025 12:00:00 PM
Airside Construction Taste of Belgium 4/2/2025 12:00:00 AM 8/29/2025 11:45:00 PM
Airside Construction RW 18C-36C Rehabilitation 4/8/2025 12:00:00 AM 6/19/2025 12:00:00 PM
Airside Construction PBB Replacement New Glycol Central System 11/1/2024 7:00:00 AM 6/6/2025 5:00:00 PM
Airside Construction Frontier Boarding Level Offices 4/14/2025 12:00:00 AM 7/31/2025 11:45:00 PM
Airside Construction PBB Project - Demo Glycol Piping at B. Basement 4/10/2025 7:00:00 AM 8/6/2025 5:00:00 PM
Off Airport Construction Resurfacing Project on Airport Access Road (KY212) 4/21/2025 8:00:00 PM 6/30/2025 6:00:00 AM
Airside Construction PBB Replacement - New GPU Tie-In 2/17/2025 7:00:00 AM 10/15/2025 5:00:00 PM
Airside Construction Dunkin' - B Concourse 4/22/2025 12:00:00 AM 7/31/2025 11:45:00 PM
Airside Construction A4 Conex Box 4/24/2025 12:00:00 AM 8/29/2025 11:45:00 PM
Airside Construction American Tower - Verizon Phase 4/28/2025 12:00:00 AM 6/30/2025 11:45:00 PM
Airside Construction Aurrigo Autonomous ULD Testing 9/9/2024 12:00:00 AM 6/30/2025 11:00:00 PM
Conveyance Outage Escalator 3-2B removed from service 4/28/2025 8:45:00 AM 10/31/2025 12:00:00 PM
Landside Construction Contractor mulching 5/12/2025 7:00:00 AM 6/6/2025 12:00:00 PM
Airside Construction ARFF Foam System Demolition 5/19/2025 12:00:00 AM 6/6/2025 11:45:00 PM
Landside Construction Amazon Hub Secure Access to Parking Project 5/19/2025 8:00:00 AM 10/31/2025 12:00:00 PM
Airside Construction Underground Storage Tank Replacement - Gate A4 5/27/2025 9:00:00 AM 6/16/2025 5:00:00 PM
Conveyance Outage Powerwalk State Required Inspections on A-P7 & 8 6/1/2025 12:00:00 AM 6/4/2025 3:30:00 PM