Location | Event | Start Date | End Date |
---|---|---|---|
Landside Construction | KY236 (Donaldson Highway) Widening Project | 2/27/2023 7:30:00 AM | 9/30/2025 5:00:00 PM |
Airside Construction | PBB Replacement & Central System Renovation Proj. | 3/31/2023 7:00:00 AM | 6/27/2025 5:00:00 PM |
Landside Construction | DHL 50 Acre Site Development | 4/22/2024 7:00:00 AM | 10/31/2025 6:00:00 PM |
Landside Construction | Fuel Farm Upgrade - Phase 7 | 12/2/2024 7:00:00 AM | 12/31/2025 5:00:00 PM |
Landside Construction | North Cargo Development Site | 8/12/2024 7:00:00 AM | 4/30/2025 7:00:00 PM |
Off Airport Construction | Traffic Switch on Donaldson Highway | 12/4/2024 12:00:00 PM | 8/30/2025 12:00:00 PM |
Landside Construction | Fiber, Energy & Dynamic Sign Project | 1/3/2025 7:00:00 AM | 4/30/2025 5:00:00 PM |
Conveyance Outage | Escalator A-2A unit out of service | 1/15/2025 12:00:00 AM | 4/7/2025 12:00:00 PM |
Airside Construction | Imbus Roofing A Concourse Warranty repair work | 1/23/2025 9:00:00 AM | 4/11/2025 4:00:00 PM |
Landside Construction | Duke Energy Utility Pole Replacement | 3/4/2025 8:00:00 AM | 5/7/2025 4:00:00 PM |
Airside Construction | Delta UPS Replacement Project | 2/23/2025 9:00:00 PM | 4/30/2025 12:00:00 PM |
Airside Construction | PBB Central System - Glycol | 11/1/2024 7:00:00 AM | 4/1/2025 5:00:00 PM |
Airside Construction | PBB Central System - GPU | 2/17/2025 7:00:00 AM | 4/21/2025 5:00:00 PM |
Airside Construction | PBB Mech Room Systems Replacement UPDATE | 9/2/2024 7:00:00 AM | 4/11/2025 5:00:00 PM |
Airside Construction | CONC. B PBB IOPS SYSTEM INSTALL | 3/4/2025 7:00:00 AM | 5/2/2025 4:00:00 PM |
Off Airport Construction | Evening/Overnight Rolling Roadblocks on I-275 | 3/3/2025 9:00:00 PM | 4/30/2025 12:00:00 AM |
Airside Construction | PBB GLYCOL COOLING SYSTEM | 3/12/2025 7:00:00 AM | 5/15/2025 5:00:00 PM |
Airside Construction | O'Rourke BHS Demo | 3/17/2025 12:00:00 AM | 4/30/2025 12:00:00 PM |
Airside Construction | Delta Maintenance Hangar De-Ice Truck Parking Work | 3/19/2025 12:00:00 AM | 4/4/2025 12:00:00 PM |
Conveyance Outage | Escalator state required inspections on 3-2B 3-2D | 4/2/2025 11:00:00 PM | 4/3/2025 3:30:00 AM |
Airside Construction | Replace flooring in N. ARFF | 3/26/2025 7:00:00 AM | 4/1/2025 4:00:00 PM |
Airside Construction | Glass repairs | 4/1/2025 8:00:00 AM | 4/1/2025 4:00:00 PM |
Airside Construction | Glycol Control Box Replacement | 3/31/2025 7:00:00 AM | 4/11/2025 5:00:00 PM |
Landside Construction | Paint restriping at ticketing and baggage | 3/28/2025 12:00:00 AM | 4/11/2025 12:00:00 PM |
Off Airport Construction | Maintenance Project on Petersburg Road (KY 20) | 3/28/2025 7:30:00 AM | 4/6/2025 3:30:00 PM |
Landside Construction | Main Terminal Cooling Tower Motor Replacement | 4/3/2025 8:00:00 AM | 4/3/2025 4:00:00 PM |
Off Airport Construction | I-75 Rolling Roadblocks (Duke Energy Repairs) | 3/31/2025 7:00:00 AM | 4/15/2025 5:00:00 PM |